President's Message
Neighbors, thank you to everyone who attended our Annual Members Meeting on September 21, either in person or virtually. Your involvement and input matter immensely to the success of our community.
We have accomplished a lot of much-needed projects this year to maintain and enhance our property. Inside this issue, you will find comprehensive highlights from both our Annual Meeting and the September 14 Board Meeting. We also cover our ongoing planning tracks for the Phase 3 project, the adopted 2027 budget, and important seasonal maintenance initiatives.
Thank you for your continued support and cooperation in keeping our community thriving.
Phase 3 Remediation Update
The Board continues to work diligently on the planning of the Phase 3 building envelope remediation. We are moving forward along two distinct decision tracks to finalize this vital project: validating costs and exploring assessment options.
Track 1: Cost Validation
To ensure the financial responsibility of this project, the Board has actively solicited cost validation and recently approved an independent Opinion of Probable Cost (OPC) directly from the Association's Engineer, which was discussed and approved at the September 14 Board Meeting. Furthermore, as part of our contract due diligence, we reached out to three additional commercial contractors for market validation based on the finalized CTETS design, and we are currently engaging with the one that responded.
Because we have opted for a CMAR (Construction Manager at Risk) delivery model, our bottom line is that "best value" means much more than just pricing. This is why we are carefully validating costs and ensuring high-quality work rather than simply selecting the lowest bidder. The Board is committed to thoroughly validating all costs before moving forward, and no final decisions or votes on the contract have been made at this time.
The Board requested and has obtained the following cost driver breakdown for the project from Reconstruction Experts, which we are sharing with the ownership:
| Cost Category | Amount | Description |
|---|---|---|
| Initial Draw / Mobilization (25%) | $395,283.31 | Upfront funding for project startup, equipment reservations, deposits, and site protection. Mobilization also includes items from below to begin initial work and would support costs for the first phases of construction. |
| Supervision & General Conditions | $223,511.87 | On-site management, fencing, cleanup, and temporary facilities. |
| Equipment & Access | $82,687.50 | Rental, fuel, and delivery for material handling/access. |
| Construction Labor | $461,818.97 | Represents ~58% of the direct construction work. |
| Construction Material | $329,237.85 | Represents ~42% of the direct construction work. |
| Project Allowance | $88,593.74 | Set aside for unforeseen conditions (will be tracked and reconciled). |
| TOTAL BASE COST | $1,581,133.24 | (Includes the contractor's 20% O&P embedded throughout) |
Important Note: Please note that this validation is strictly for the base costs. When factoring in additional budgeted funds for engineering, permits, and an estimated 20% contingency for unknown conditions (such as hidden rot and sheathing), the current total estimated budget for a single-phase project (Option 1) is $1,956,733.49. The Board has not landed on the final contingency percentage given the project allowance already included from RE, so this final amount is subject to change. Additionally, this estimate assumes a January start, completing the project all during the same time period.
Track 2: Assessment Options
Based on homeowner requests, the Board has sought advice from our attorney to determine if it is an option to assess the project differently than the standard 1/63 allocation—such as based on the benefit received or the specific scope of work completed on each unit. Other shared costs, such as contingency, engineering, and permitting, would still likely be allocated 1/63.
What Does This Mean For Me?
We have published initial assessment options on our official projects page and will continue to add any new ones to help owners plan. The Board is still targeting December 2026 for the first payment, but owners will be provided the required 30 days' notice prior to the effective date/first payment. No final decisions or votes on the contract or exact assessment structure have been made yet.
Coordinated Maintenance Projects
We have a few remaining projects for the year that we are strategically holding off on to coordinate directly with the Phase 3 project. These include the painting of the parapet caps (which are now officially part of the Phase 3 scope) and the caulking of vertical control joints on the building infrastructure. By waiting, we hope to utilize the Phase 3 lifts to perform this work and achieve significant cost efficiencies.
Bookmark the Projects Page!
We encourage everyone to bookmark our official projects page: thevinehoa.org/projects. Please visit it regularly for the latest information. It is the best place to find real-time updates between our regular community updates and newsletters!
2027 Budget Overview
At the Special Organizational Meeting held immediately following the Annual Meeting, a motion was made by Chris Nicks to adopt the 2027 Budget, which was unanimously adopted by the board.
$595 / month
2027 Monthly Assessment
Budget Highlights
- The new 2027 monthly assessment of $595 represents an increase of $20 per month, or 3.48%.
- Under the new budget expenses by category, Taxes, Insurance, and Reserves will account for 48% of total monthly dues.
- The 2027 reserve funding commitment is set at $104,000. This is composed of $54,000 in new annual contributions and a $50,000 interfund repayment obligation. This level of funding exceeds required levels for Freddie Mac and Fannie Mae as well as the recommendation in our Reserve Study.
Current financial performance can be found at thevinehoa.org/financial-transparency.
2026 Annual Meeting Recap & Board Elections
Thank you to everyone who joined us for the 2026 Annual Meeting! Whether you attended in person at Mi Cocina or virtually via Teams, it was fantastic to connect as a community, celebrate our recent accomplishments, and discuss our shared future. For those who couldn't make it, you can catch up by watching the full recording on our official YouTube channel.
Celebrating Our 2026 Accomplishments
President Erik Stanford kicked off the meeting by reviewing the extensive property improvements completed over the last year. We've successfully checked off several major enhancements:
- Carlisle Landscape Project: This multi-year beautification effort, which began in 2024, is now officially complete, significantly elevating our street-facing presence.
- Exterior Building Washing: A comprehensive, community-wide power wash was completed to remove accumulated dirt and instantly refresh our property's aesthetic.
- Concrete Drain Repairs: Critical underground and foundational work was finished, specifically impacting Units 31 through 34, to mitigate immediate water management risks.
- Sewer Cleanout Caps: Broken sewer cleanout caps that had fallen into the pipes were excavated and replaced. This ensures our plumbers have immediate access during backups, significantly lowering emergency response costs and preventing extensive damage.
Completed landscape enhancements at the corner of Carlisle and Bowen.
Open Forum Q&A & Neighborhood Development
During the Open Forum, we had a robust discussion driven by great homeowner questions regarding the upcoming Phase 3 project, funding alternatives, and neighborhood changes:
- Neighborhood Construction Updates: Tony Page, a Vine owner and former Board President, provided a highly informative and comprehensive update on the surrounding high-rise, hotel, and commercial real estate developments actively impacting our neighborhood, such as the projects at Hall and Carlisle and Hall and Bowen. It was a great look at how our area is evolving!
- Funding & Capital Loans: When asked about exploring capital loans as an alternative to special assessments, the Board explained that preliminary analysis indicated significant added costs to all owners, making short-term capital loans cost-prohibitive.
- Project Phasing: Homeowners inquired about stretching the Phase 3 project timeline. The Board noted that while pacing options are under review, the active water intrusion into several units makes significant delays risky.
- Lintel Repairs: The Board provided clarification regarding the 30 garage door lintels that were fully replaced during Phase 1 versus the 33 remaining lintels that currently require reflashing.
Rendering of the upcoming office building development at Carlisle and Bowen.
2026 Board Elections & Officers
We are thrilled to announce that current members Mark Allen and Erik Stanford were re-elected to the Board in an uncontested election. The President (Erik Stanford) and Secretary (Chris Nicks) each have one more year on their term, so they will continue in their current officer roles. At the Special Organizational Meeting immediately following the Annual Meeting, Robbie Flowers nominated Mark Allen to continue serving as Treasurer, which was unanimously affirmed by the board.
Get Involved!
We need your participation now! There are different levels of involvement you can take on based on your schedule. You can engage with a "light touch" by answering community surveys, or take a moderate role by joining the Landscape, Social, or Maintenance committees. We also have great opportunities to step up and participate in our third annual holiday decoration contest and join the decorating committee to install the community holiday decorations. The decorating committee will begin their work the weekend following the Thanksgiving holiday.
Email Us to Join a Committee2026-2027 Meeting Schedule
A motion was made to adopt the 2026-2027 Board and Annual Meeting Schedule with the ability to make changes with sufficient notice. The Annual Association Meeting is scheduled for September 20, 2027 at 6:30 PM. Upcoming regular board meetings are scheduled for 6:30 PM on:
- Nov 9, 2026 (Note: This date may be adjusted due to board member travel)
- Jan 11, 2027
- Mar 8, 2027
- May 10, 2027
- Jul 12, 2027
- Sep 13, 2027
Non-Routine Maintenance & Repairs
A look at the non-routine maintenance performed this quarter to keep our community and shared amenities running smoothly:
Recently restored and re-stained community wood fence.
-
Wood Fence Repair, cleaning, and re-staining of the community wood fence. (Note: Only the first draw was paid this quarter; the remainder will be paid in September).$7,140.00
-
Pool Gates Refurbishing and painting 2 pool gate doors and mounting an electrical box.$315.00
-
Lighting Comprehensive repair of pool area landscape lighting system and exterior bulb replacements.$2,963.97
-
Drainage & Plumbing Cleaning and flushing of storm and landscape drains, plus clearing 4 additional drain lines.$2,362.50
-
Irrigation System repairs including replacement of heads, valves, and solenoids.$1,069.26
-
Pool Facilities Installation of new in-line chlorinator, flow meter clamps, filter cleaning, and system checks.$906.00
-
Safety & Security Installation of new parking signs, commercial re-keying of pool restroom, and display case locks.$863.60
-
Debris Haul Away Removal of illegally dumped furniture, appliances, and general debris cleanup.$368.06
Unit Maintenance Checklist
Gutters
Check unit gutters to ensure they are free of obstructions and clean any debris that may be blocking them.
HVAC
Replace HVAC air filters regularly and schedule a professional furnace checkup before winter.
Roofing
Inspect your roof or schedule a professional inspection to look for damage. Ensure flashing is secure and appropriately sealed.
Detectors
Check all smoke detectors and replace batteries if needed.
Dryer Vents
Inspect dryer vents and remove lint buildup to prevent fire hazards and improve efficiency.
Weatherstripping
Inspect the seals around your windows and doors for drafts. Replacing worn weatherstripping will help keep the warm air in and lower your winter heating bills.
Pool Maintenance Update
We continue to get sand and other debris in our pool resulting from the active construction site behind our property. The Board is investigating adding additional cleanings if they are deemed necessary to protect the pool equipment. Currently, the pool is being cleaned properly (and our pool service sends us pictures once the cleaning has been performed to verify), but when the construction crews are actively working, the sand and debris are unfortunately back by the end of the day.
Before Cleaning
After Cleaning
Questions or Requests?
Submit account inquiries, maintenance or ARC requests, and general questions through the official Portal.
Log into PortalNeed Portal Access Help?
Contact Customer Care at:
customercare@worthross.com
855-435-4596
(Mon–Fri, 9 a.m.–6 p.m.)
Connect With Us
Have feedback on this newsletter or suggestions for a future issue?
Submit it here.
Find us online at:
thevinehoa.org